Project is an addition to an existing detention facility and includes two segregation units, eight dormitory units, Booking, Intake, and Release, Law Enforcement support facilities, and Security Electronics upgrades to the existing facility. Engineering responsibilities included internal communications, card access, door monitoring and control, closed circuit television, digital video recording and personal alarm. Total estimated project cost is and estimated $132 million and the Security Electronics systems costs is estimated $8.2M. This project was completed in March 2011.
New 720 bed jail, system upgrade of original 256 bed jail, and courts addition. $132M Construction Cost
Central Control with two positions
Created New Central Control and back up of Central Control